Issue 01 · Electrification
The current is the chain
800 V DC AI factory electrical chain from grid to chip
At 600 kW, 48 V is 12,500 A. 800 V is 750 A. NVIDIA names about 5%. The rest of the book is copper, conversion, and the building.
30 Aug 2026 · 8 min · 1:37 listen · /industries/800v-dc.md

NVIDIA captures the chip. The building captures the current. Price the phase, not the logo.
Desk view · cite the URL
Listen
Night briefing
Atlas · 1:37 · not a keynote
The chain
Grid to chip
09 steps
I · 2026–27
Sidecar retrofit
II · 2027–28
Native 800 V compute
III · Late 28–29
Building-scale DC
IV · After 2029
Solid-state transformer
X desk
It broke there first
The map lands on X. The missing column usually sits in a reply. We sit both, then write the view.
Still open on this chain
Inbound. Not yet a sitting.
25 Nov · 09:30 · @everything_PE_Source · Open · @wireJereh has launched the PowerVEGA solid-state transformer for AI data centers, delivering 3 MW per unit with medium-voltage direct connection and integrated power conversion and distribution. The unit converts 13.8 kV AC to 800 V DC at 98.5 percent peak efficiency, uses 2300 V SiC modules, and supports direct gas-turbine coupling with factory prefabrication for eight-hour on-site commissioning.
@everything_PE_ · Thread had no replies. Residual is conversion of the 3 MW PowerVEGA launch into disclosed shipment volumes and qualification clocks against the 800 V hall clock.
Jereh captures the 3 MW solid-state transformer step for AI data centers with the PowerVEGA SST, delivering 800 V DC from medium-voltage AC at 98.5 percent peak efficiency with direct gas-turbine coupling, launched at RE+ 2026.
26 Nov · 00:00 · @OptionKing666Source · Open · @wire800V DC power architecture adoption is set to jump from 16% of new data center capacity in 2027 to 79.1% by 2030, Citi estimates, marking an irreversible structural shift away from traditional AC distribution. Total 800V DC capacity is projected to surge from 4.3GW in 2027 to 32.2GW by 2030. Within the 800V DC buildout, solid-state transformer (SST) architecture represents the premium greenfield tier, with analysts estimating SST-based capacity will climb from near-zero in 2026 to 17.8GW by 2030, capturing 55.4% of all new 800V additions. In the interim, retrofittable Sidecar 800V DC solutions serve as a bridge for existing facilities, peaking during the 2028–2029 transition window before purpose-built SST systems take over.
@OptionKing666 · Thread had no replies. Residual is conversion of the Citi 2030 SST and Sidecar clocks into disclosed supplier names and absolute volumes against the 800 V hall clock.
SST architecture captures the premium greenfield 800 V DC tier, climbing from near-zero in 2026 to 17.8 GW by 2030 and 55.4% of new 800V additions, while Sidecar solutions bridge existing facilities peaking in 2028–2029 per Citi estimates.
26 Nov · 08:42 · @TimestechBuzzSource · Open · @wireVertiv is expanding its power infrastructure portfolio to support rising AI computing demands across the rack, compute pod and data hall. The expanded 800 VDC portfolio includes the PowerDirect 5000 Power Rack (up to 800 kW, 480 VAC to 800 VDC or ±400 VDC), PowerDirect 3000 90 kW DC-DC shelf, PowerDirect 9000 1.5 MW Power Center with DC busway for pods, and PowerNexus MV SST 5 MW solid-state transformer for data halls converting medium-voltage AC directly to 800 VDC. Pilots and technical validation are underway.
@TimestechBuzz · Thread had no replies. Residual is conversion of the multi-level 800 VDC portfolio and ongoing pilots into disclosed customer volumes and qualification clocks against the 800 V hall and rack clock.
Vertiv captures the 800 VDC power architecture step from rack (PowerDirect 5000/3000) through pod (PowerDirect 9000 1.5 MW) to data hall (PowerNexus MV SST 5 MW), with pilots underway as of 26 Nov 2026.
25 Nov · 07:30 · @dolphinR123Source · Open · @wireFrom a global bank's note: Jereh has signed about 16.4 bn yuan of data center power equipment orders this year, its largest ever for one business line, at gross margins above 60%. Delivery lags orders by about two quarters, so most of the revenue lands in 2027. Relay maker Hongfa has 800V data center power moving from pilots to first small orders with global tech customers.
@dolphinR123 · Thread had no technical replies. Residual is the absolute order volume and customer names behind Hongfa's first small 800V orders and Jereh's 2027 revenue conversion.
Hongfa captures the 800V DC power relay step, moving from pilots to first small orders with global tech customers, while Jereh captures data center power equipment with 16.4 bn yuan of orders this year and most revenue landing in 2027.
24 Nov · 23:51 · @voicendata_Source · Open · @wireInfineon Technologies and Megmeet are collaborating on 800 VDC power systems for AI data centres, covering key components such as server power supply units. Megmeet will use Infineon's CoolSiC MOSFETs G2 in its three-phase AI power shelf, with the collaboration also covering intermediate bus converters and solid-state transformers.
@voicendata_ · Thread had no replies. Residual is conversion of the 19 Nov collaboration into disclosed shipment volumes and qualification clocks for the three-phase shelf.
Megmeet captures the three-phase AI power shelf step for 800 VDC architectures using Infineon's CoolSiC G2 MOSFETs, with the collaboration covering PSUs, IBCs and SSTs.
Sources
Short
Nine by sixteen. One line.

0:15
12,500 A at 48 V. 750 A at 800 V. The building takes the rest.
Notebook
Pack for NotebookLM
Google does not give the desk a generate-overview pipe. Copy the pack, drop it in a notebook, and let their voice sit beside ours.
House
Sit the next issue. Print the chain.
A house underwrites one map — electrification, physical AI, the picks that do not trend until the assembler does.